The list of change orders for May has been published on
the agenda for Monday, May 13, 2013. They are as follows:
Change Orders for High School Renovation Project – The following change orders are presented for Board consideration. All the change orders listed below have been reviewed by the architect, PJ Dick and the District administration.
a. EL-26-84 to Farfield for $3,038 to replace LED fixtures on Bldg F 5th floor Lobby,
b. GC-35-85 to Nello for $2,857 for closure plate on H-4 stairs,
c. GC-36-86 to Nello for $7,039 to remove diagonal bracing in F Building,
d. GC-37-87 to Nello for $37,404 to finish stairwells and drywall in F Building on a time and materials basis (April work),
e. GC-38-88 to Nello for $6,023 for bent plate modification at G Building where it meets F Building – unforeseen condition,
f. GC-39-89 to Nello for $7,406 for south parking lot concrete wall height increase,
g. GC-40-90 to Nello credit for ($550) for entry mat changes in all buildings,
h. GC-41-91 to Nello for $1,749 to change swimming pool bulkhead in seating area,
i. GC-42-92 to Nello for $2,003 for removal of steel from roofing,
j. GC-44-94 to Nello not to exceed $26,911 for joist modification in the athletic facility on a time and materials basis,
k. GC-45-95 to Nello for $12,563 for temporary grading and asphalt to reopen Horsman Drive related to rework of loading dock,
l. GC-46-96 to Nello for $6,676 to shore roof in G Building at F Building for missed steel beam,
m. GC-47-97 to Nello for $847 for door and door hardware modifications and addition of four Knox boxes for fire department,
n. GC-48-98 to Nello for $16,275 for additional fire extinguishers added by Municipality,
o. EL-27-99 to Farfield for $5,318 for concrete around conduit instead of stone,
p. EL-28-100 to Farfield $3,231 to re-pull and terminate voice and video feeds in the Little Theatre, and
q. GC-49-101 to Nello for $75,000 for winterization costs.
The total amount for May is $213,790.00.
4 comments:
$75,000 for winterizarion costs.
I can see the discussion.
The board: What is this winterization cost of $75gs?
CM: "Just a little oversight, we overlooked that winter in Pennsylvania sometimes gets very cold!"
Unbelievable!!!!!
It's just other peoples' money...
Winterization in construction is dealing with excessive rain and stabilizing soil thru wet weather and freeze and thaws.
This $75,000 is not really a change order since the project is scheduled to run over at least four years and winters in Pittsburgh are well known to be wet and snowy. Winterization should have been factored in the original bid, then if it wasn't used up rebated.
This CO wouldn't have anything to do with that improperly seated beam that made the gym floor uneven would it?
j. GC-44-94 to Nello not to exceed $26,911 for joist modification in the athletic facility on a time and materials basis,
Post a Comment