When the cost of the project came back too high, our school board elected to cut corners by considering 197 potential project cost saving reductions. The list represented approximately $14 million in potential savings. How much of this has come back to haunt us? Back on August 8, 2011, I noticed that the school board agreed to eliminate the storm water detention tanks (#17). The rain garden was nixed as well. This had a direct impact on the stormwater situation on Cedar Blvd. After Cedar Blvd. flooded on August 3, 2014, and then again nine days later, I asked Gateway's Dan Deiseroth if the high school renovation was contributing to the flooding on Cedar. His answer was, "No." I asked Dan if he OK'ed the high school renovation plans. His answer was, "Yes." Gateway approved this cut! This is the same person who said that the fields don't flood; it is merely standing water.
Another item cut was #23 Eliminate need for pyrite remediation based on geotechnical report. We know how that ended up.
A third critical decision made by the school board was #40 Change glass rail at swimming pool to stainless steel airplane cable rail. As we know, that produced a change order. But look how it was handled.
Will we need another change order for the change order? Will we get the nuts and bolts in the next change order?
Lebo Citizens, please review the 197 potential project cost saving reductions and see if more questionable choices resulted in change orders.
Finally, readers have been wondering about the status of the Pursuant Ketchum fundraiser. We are still in the quiet phase, two years later. The September 14, 2014 Personnel Report shows that the full time director of the capital campaign will be on a leave of absence and an interim director has been hired at a daily rate of $300. The interim director's employment is late September 2014 through early January 2015. The present campaign director will be on leave starting October 8, 2014 through the beginning of January 2015. Is the overlap in employment and buying additional fundraising software really necessary? We invested in a Feasibility Study. Or will we be chalking this up to more contentious decisions made by our school board?
Get the railing fixed!!!! It was first reported November 19, 2013!
Update September 30, 2014 9:44 AM Read the snarky reply from Dr. Steinhauer concerning the pool railing.
From: TSteinhauer@mtlsd.net
To: David Huston
Subject: RE: Missing hardware on new pool balcony railing
Date: Tue, 30 Sep 2014 12:17:21 +0000
Dear Mr. Huston,
Thank you for contacting the Board with your concerns. Installation of the revised pool railing is not complete. The lack of 2 bolts presents no structural or physical safety issue and will be installed when the project is completed. If this makes you uncomfortable, please stay away from this railing section until it is complete.
We are aware of no safety issues with construction.
Timothy J. Steinhauer, Ed.D.
Superintendent of Schools
Mt. Lebanon School District
412-344-2076
What did you do today to improve the life of a child?