The agenda for Monday's school board meeting has been posted. It includes
PlanCon Part I for High School Renovation Project – PlanCon Part I is required to be submitted for change orders on the project. There are two submissions presented for the Board’s approval as completed by Celli Flynn Brennan Architects. The Superintendent recommends approval of these submissions.
Change Orders for High School Renovation Project – This month’s list of change orders totals $127,994 from the contingency and $4,561 from soft costs for the high school renovation project. The change orders are as follows:
a. GC-107-252 to Nello for $114,842 for excavation, masonry, walls, supports, beams and steel and brick modifications,
b. EL-70-253 to Farfield for $3,459 for electrical and power changes,
c. FP-06-254 for SimplexGrinnell for $5,512 for sprinklers,Naming Rights Policy
d. ME-28-255 to McKamish for $4,181 for ductwork, cabinets and fans, and
e. EL-71-256 to Farfield for $4,561 for phone change.
The Superintendent recommends approval of these change orders.
Revisions to Policy FF, Naming Rights – The Policy Committee is recommending approval of revisions to Policy FF, Naming Rights, at the November 17, 2014 Regular Meeting.