Also, here are the notes from the Construction Update on September 10, 2012 concerning change orders:
Construction Update Change Order Conversation from 9/10 Notes
Due to complexity of issues they have encountered they have started weekly meetings with Celli-Flynn to make everyone aware of everything that is out there.
#1- $63000 Nello Const due to moving sewer lines due to request of municipality. Dan Remely completely blamed municipal engineer for increased cost. "Municipal Engineer did not do his job when he approved the plan". Posti chimes in blames the municipal engineer for not being familiar with the paving ordinance. "Why did they not have the specs for the pavement itself....who did not catch that?". Marciniak says the trench ended up having to be dug wider and there were some unforseen conditions on subbase and had to go to subgrade which made this a bigger deal. Posti say municipality may have paved the street with subpar subbase that the SD has to replace. Sounds like what Rick said is true...contractor simply had to dig a bigger hole. But both Dan and Posti would rather point the finger at the municipal engineer.
#2- $30,000 to Nello for work required to relocated storm and sewer lines to clear way for new foundations in athletic and science buildings. Shouldn't the drawings have show this?
#3- Fairfield Electric for duct bank incoming feed for DQ Light for Athletic and Science. Add two pipes and duct bank. DQE looked at loads required by science builing required additional feed. Saved $200,000 on bid but came back $60,000 on the other end per Dan's math.
#4 IT department Fairfield electric add $12000 for cable feed from B Building to MDF in F building. Running Cat3 (phone) cable instead of Cat5 (data).
#5 Vrabel Plumbing $17,000 site utlity conflicts with caisons and side beams. Shouldn't the drawings have shown this?
#6 $25,000 credit to use PVC piping instead of copper for pipes 2.5 inches or smaller in non-plenum rated spaces. All PVC will be indoor. Shouldn't the drawings have shown where they could use indoor PVC vs outdoor rated copper?
#7 Nello $11,000 change one retaining wall for frost depth and $5000 to replace unsuitable material with concrete. Board blames the architect.
Ed with Pyrite...south end of science building and north end of building. Seems to be limited to these sites at this time. Another half to pyritic soil change that has yet to be submitted.
Fairfield $272,000 related to 5kV power loss. OSEPA or Builders Insurance Claim so it should not affect the project. Costs through 8/31. Generators taken offline day before meeting. 8/31-9/9 costs not yet submitted. Emergency repair would NOT be part of budget and likely will be covered by insurance as well. At most the District will be on the hook for the deductible per a question by Goldman.
Original change order for dirt may be gone...using rockpile dirt for fill now so costs from a few months back should be greatly reduced.
Something else I found out, OSHA has something to say about repairs to anchor bolts of columns. http://www.osha.gov/pls/oshaweb/owadisp.show_document?p_table=INTERPRETATIONS&p_id=25178
Section 1926.755(b) requires the following:
(1) Anchor rods (anchor bolts) shall not be repaired, replaced or field-modified without the approval of the project structural engineer of record.
(2) Prior to the erection of a column, the controlling contractor shall provide written notification to the steel erector if there has been any repair, replacement or modification of the anchor rods (anchor bolts) of that column.
According to §1926.752(a)(2), where anchor bolts have been modified, the controlling contractor must inform the erector that the modification has been done in accordance with the requirements under §1926.755(b). Section 1926.755(b) has two requirements: (1) no repair, replacement or modification shall take place without the approval of the project structural engineer of record, and (2) the erector must be informed in writing that there has been a repair, replacement or modification.I got a response today for my Right To Know:
Mt. Lebanon School District ("the District") is in receipt of your Public Records Request form dated September 6, 2012, which requests, pursuant to the Right to Know Law ("RTKL"), all daily inspection reports from the project’s testing and inspection firm concerning site work for the high school construction project.
Please be advised that the District requires additional time beyond five business days to respond to your request pursuant to Section 902 of the RTKL.
An extension of time is required because the extent and/or nature of the request preclude a response within the required time period.
The District expects to provide a written response to your request and have any responsive public records available within thirty (30) days of today's date, the records are available at an earlierdate.