That is what the Sports Advisory Board is calling the turf project for Middle and Wildcat Fields.
Sports Advisory Board Video from Feb. 6, 2014
A presentation will be made to the commission on
Tuesday, February 11, 2014 at 6:15 PM. Notes from the presentation are:
Fundraising YTD $56,500 Target is $250,000
Contributions include:
$47,500 from Sports Associations
$5,000 PAC
$4,000 from an anonymous donor (Gateway?)
Contributions are being handled by Mt. Lebanon Community Endowment.
Signage revenue would be considered as non-municipal contributions
Recommended fee schedule:
Recognized Mt. Lebanon Sports Associations would be charged $15/hour per field. It is estimated that a minimum of $12,000 in fees collected annually would be allocated for turf replacement.
In lieu of fees, MTLSD would be responsible for field maintenance.
Vendor List 1/15/14 meeting
Field Turf
Astro Turf
Shaw
Prograss
Some vendors from 1/15/14 also sell organic fill turf, and none spoke highly of organic fill turf. Organic fill (coconut shells and cork) tends to float away. It freezes. There is a tendency for "stuff" to grow in it and would need a pesticide treatment. It also decomposes.
Vendor List 2/7/14 meeting
GeoTurf organic fill turf
Project Schedule
Design Development - pending Commission approval Feb./March 2014
Construction Documents & Specifications April/May 2014
Advertise Bids May 15, 2014
Open Bids June 4, 2014
Award Bids at either the June 10 or 23rd Commission Meeting
Begin Construction July 15, 2014*
Completion Date October 21, 2014
*Flexible may be August 1, 2014
There was discussion of potential capital projects using more unassigned funds. Everyone was in agreement that McNeilly is out of the question. Dave Franklin was silent. Also, instead of buying a mower for the golf course, a number of smaller projects could be completed instead.
My takeaway: Organic turf is not an option. We'll see what my RTK reveals, if it ever gets granted.
Update February 9, 2014 10:25 AM Organic infill would be an Add/Alternate.