a. GC-111-270 to Nello for $31,361 for doors, hardware and partitions,
b. EL-77-271 to Farfield for $23,846 for conduits, door openers, power changes and light fixtures,
c. EL-78-272 to Farfield for $4,396 for power and data lines in new library,
d. GC-112-273 to Nello for $1,173 for glass and door work,
e. IN-11-13 to Nello for $41,951 for repairs to damaged wood floor,
f. IN-12-14 to Farfield for $15,758 for repairs for water damage, and
g. ME-33-274 to McKamish for $2,660 for fume hood.
Additionally, the Board is asked to permit the transfer of up to $538,000 from the FF&E Soft Cost Budget to the Contingency Budget. The Superintendent recommends approval of these change orders and the budgetary transfer.