Change Orders for High School Renovation Project – The following change orders are presented for Board consideration. All the change orders listed below (totaling $244,386) have been reviewed by the architect, PJ Dick and the District administration.
a. GC-85-182 to Nello for $22,394 for fine arts building design coordination,
b. GC-86-183 to Nello for $24,717 for athletic wing window pockets and new
beam,
c. GC-87-184 to Nello for $19,516 for B building code revisions ,
d. GC-88-185 to Nello for $17,445 for time & materials on doors jamb corrections,
e. FP-04-186 to SimplexGrinnell for $10,081for phasing and changes in rated walls,
f. ME-16-187 to McKamish for $25,430 for added duct in Little Theatre,
g. PL-24-188 to Vrabel for $22,955 for courtyard storm work,
h. PL- 25-189 to Vrabel for $21,162 for phasing relocation of utilities,
i. EL-50-190 to Farfield for $6,348 for changes to walls and added electrical
controls,
j. EL-51-191 to Farfield for $29,973 for sound system in Little Theatre,
k. EL-52-192 to Farfield for $27,924 for lights changes, chiller and duct work, and
l. GC-89-193 to Nello for $16,441 to phasing change on structure demolition.