High School Project Change Orders – A number of change orders for the High
School Renovation Project are presented for Board action next week. All have
been reviewed by the architect, construction manager, Rick Marciniak and Jan
Klein and are recommended for approval. They total $231,611.08 and are as
follows:
a. Change order #ME-01-15 to McKamish for $1,502 for additional drafting coordination for Boiler Room
b. Change order #AB-02-17 to Precision Environmental for $71,999 for demolition and abatement of interior partitions that were initially thought to be asbestos free in the bid documents
c. Change order #GC-07-18 to Nello for $9,206 on a time and material basis for demolition of corridor ceilings on the 6th floor of B-Building once it was determined that the corridor steel would have to be fireproofed
d. Change order #EL-03-19 to Farfield for $3,210 to remove an existing light pole and replace it with a junction box
e. Change order #EL-04-20 to Farfield for $14,850 to extend the power lines to condensing units moved from ground to roof
f. Change order #GC-08-21 to Nello on a time and materials basis which will not exceed $36,228.50 without further Board approval to fireproof the steel structure at the 6th floor B-Building corridors of Area B
g. Change order #GC-09-22 to Nello on a time and materials basis which will not exceed $22,945.23 without further Board approval to infill an area of about 34’ by 34’ with lath and plaster or gyp board as possible in the 6th floor B-Building Area
h. Change order #GC-10-23 to Nello on a time and materials basis which will not exceed $25,658.35 without further Board approval to provide plaster patching for a fire rating in 6th floor B-Building classrooms (excludes the area listed above)
i. Change order #GC-11-24 CREDIT to Nello Construction for -$5,297 for demolition of those same partitions which were part of their original work, but eliminated once they had to be abated
j. Change order #GC-12-25 to Nello Construction for $42,058 for added bulkhead to the ceiling of the 6th floor due to its being lowered
k. Change order #GC-13-26 to Nello Construction for $9,251 for additional roof curb flashing in the B-building due to the change in HVAC rooftop units
According to my running total, change orders are up to $954,803.65.